Construction Progress Update:

Ms. Kelly
We’re making great strides on the campus construction project! Most of the concrete footings and walls have been poured, and utilities are now stubbed up within the building footprint. Site crews are currently preparing for the installation of the basement concrete slab on grade.
 
What’s next?  

• Construction of CMU walls   
• Erection of structural steel beams  
• Placement of concrete plank flooring
 
Stay tuned for more updates as we continue to build the future of our campus!