Construction Update: Lewis Track and Field Lighting Progress 

Eaglebrook News Team
As the snow melts and the air warms, the construction projects at Eaglebrook continue to progress. The Final stages of the stadium lighting installation at the Lewis Track and Field are underway. The footings for the light poles were installed in February, and over spring break, the light fixtures and poles were successfully placed.
 
Site work and final wiring will take place during the week of March 24. Final light aiming and control adjustments are scheduled for the first week of April. In the meantime, we expect to have the lights powered on and ready for use as early as next week, bringing us one step closer to hosting night games on the field. 
 
Stay tuned for more updates as the project progresses!
 
Check out the live cam progress of the construction of the new dining hall at www.eaglebrook.org/construction.